Starting Today we framed up some temporary rafters 8' on center to cover the slab in case of possible rain. We also used duplex nails to make sure disassembly would go quick.
Also we put a lateral brace to make sure the rafters wouldn't rack in wind.
Also we put a lateral brace to make sure the rafters wouldn't rack in wind. Openings for our foundation. The box sill has been placed.
Put the mud sills down after squaring the foundation as much as we could. There was some over hang but the foundation was very out of square. The sill seal was put down below the pt 2x6 because It is permanent.
Final pieces of rebar are put down and tied together so the rake can pull it up.