Friday, October 24, 2014

Floor framing

This week we finished putting in the joists. The stair framing was talking a long time and we just didn't have time to finish so the full length joists were put in. 
Plywood being put down and nailed. Lines were snapped at 4'-1/4" so there wouldn't be any over hang. The sheets were then laid out for 16" O.C. So the joists could be placed correctly. 


Metal bridging is used for lateral bracing, to make sure the building didn't move. And it's less time than cutting blocking 