This week the floor got finished off. The walls were built and sheathing was put on with 7penny nails. Then we had to finish them with a nail set. They went up pretty quick. 

This is the finish product, all of the walls are either 8' wide or just shy of 12'. It took some time to get them all assembled and blocking in. The double top plate was just screwed down to be temporary just like the walls were screwed Together. 


After all the work we did the walls and floor were taken apart. The sections are made for easy assembly. They are all marked so there isn't anything put up wrong. Also so the assembly is quick 